Intervener evidence has been filed in Proceeding no. 3585 on AltaLink’s 2012-2013 deferral account reconciliation application.
To view more of this post, please
Intervener evidence has been filed in Proceeding no. 3585 on AltaLink’s 2012-2013 deferral account reconciliation application.
To view more of this post, please
The Alberta Utilities Commission has rejected the Alberta Utilities’ proposal to finalize return on equity and capital structures determined in the 2013 generic cost of capital proceeding for 2016.
To view more of this post, please
On June 27, the CCA applied to the AUC requesting advanced funding for their participation in three separate proceedings: AltaLink 2012-2013 Deferral Account Reconciliation (DAR) application, AltaLink 2015-2016 GTA, and ATCO Electric 2015-2017 GTA.
To view more of this post, please
The CCA, UCA and City of Calgary (the “customers”) have jointly have responded to a proposal by the Alberta Utilities to expedite the 2016 GCOC proceeding.
To view more of this post, please
In October of 2014, the AESO submitted its 2014 ISO Tariff compliance filing as per Decision 2014-242. After initial information requests, the Commission split the proceeding into two modules so as to allow for further testing of the AESO’s compliance with Commission Directions 5-8.
To view more of this post, please
On April 30, 2015, only 6 weeks after the 2013 Generic Cost of Capital decision (applying to 2013, 2014 and 2015), the Alberta Utilities Commission issued a letter initiating the 2016 GCOC proceeding, and requesting feedback regarding the scope of the hearing and approaches to the application process. The Alberta Utilities shortly thereafter issued a response proposing an alternate approach to the 2016 GCOC.
To view more of this post, please
On December 17, 2014, AltaLink filed an application to reconcile the capital expenses of AESO direct assign projects completed during 2012 and 2013.
To view more of this post, please
Subsequent to AltaLink’s November 18, 2014 application, AltaLink filed responses to information requests in February.
To view more of this post, please
On March 9, 2015 the Commission released their decision on 2013 Generic Cost of Capital (Decision 2191-D01-2015), which lays out the Commission’s findings on a generic return on equity (ROE) and a common equity structure.
To view more of this post, please
On January 26, 2015, the AUC approved AltaLink interim TFO tariff application effective January 1, 2015 (3504-D01-2015).